Installation and Commissioning of an 80-meter Wind Mast for Wind Resource Measurement in Guadeloupe
April 14, 2019Environmental and Social Due Diligence (ESDD) on Behalf of Lenders for Solid Waste and Drain Rehabilitation Project in Egypt
March 11, 2019
Firnas Shuman was retained by a consortium of international and local developers to conduct a full-service, one-year measurement campaign for a 500 MW wind farm. Firnas Shuman supplied, installed, and commissioned the masts and is responsible for data acquisition, verification, and reporting for the full year measurement campaign
Location: Egypt
Customer: Consortium of Developers
Year: 2019
Status: Ongoing
Firnas Shuman was retained by a consortium of international and local developers to conduct a full-service, one-year measurement campaign for a 500 MW wind farm. Firnas Shuman supplied, installed, and commissioned the masts and is responsible for data acquisition, verification, and reporting for the full year measurement campaign
Location: Egypt
Customer: Consortium of Developers
Year: 2019
Status: Ongoing
Firnas Shuman team provided the following services:
- Supply of met-masts;
- Installation of the met-mast;
- Supply of the meteorological measurement sensors and data acquisition system;
- Operation and maintenance including preventive and corrective maintenance;
- Data monitoring;
- 12 month measurement campaign which was later extended to 15 months.