The project is a solar meteo-station. The tower, already purchased by the client, needed to be installed in the selected location. Installation has been successfully completed by Firnas Shuman.
Location: United Arab Emirates
Customer: Dubai Electricity and Water Authority (DEWA)
Date: 2016
Status: Complete
The project is a solar meteo-station. The tower, already purchased by the client, needed to be installed in the selected location. Installation has been successfully completed by Firnas Shuman.
Location: United Arab Emirates
Customer: Dubai Electricity and Water Authority (DEWA)
Date: 2016
Status: Complete
Services:
- Installation of a solar mete-station (including tracking unit, pyrheliometer, and shading apparatus to measure direct, diffuse, and global solar irradiation as well wind speed, direction, ambient temperature, humidity, pressure, temperature of solar modules, and impacts of soiling. The unit also included a custom-built apparatus for measurement of soiling on reference solar cells).