Due Diligence on Behalf of a Lender for 5 MW Photovoltaic (PV) Power Plant in Tanzania
January 1, 2014Feasibility Study and Conceptual Design Including Bankable Solar Resource Assessment Campaign for a 20 MW PV Power Plant in Hurghada, Egypt
September 1, 2013
The project is a pre-acquisition due diligence for a 100 MW GE Gas Turbine Facility in Al-Hartha. The client was evaluating the purchase of rental equipment and associated terms of the rental contract from GE Power and Energy (GE). The power plant consists of six TM2500 aero derivative gas turbines and selling associated services and balance of plant materials for each.
Location: Iraq
Customer: Alstom Power Rental (APR Energy)
Year: 2013
Status: Complete
The project is a pre-acquisition due diligence for a 100 MW GE Gas Turbine Facility in Al-Hartha. The client was evaluating the purchase of rental equipment and associated terms of the rental contract from GE Power and Energy (GE). The power plant consists of six TM2500 aero derivative gas turbines and selling associated services and balance of plant materials for each.
Location: Iraq
Customer: Alstom Power Rental (APR Energy)
Year: 2013
Status: Complete
Firnas Shuman team was responsible for in-country technical, environmental and social due diligence, including:
- reviewing site location, output and transportation logistics;
- reviewing the environmental and social impacts and reporting on-site observations;
- evaluation of operations, maintenance, spares, procedures, and staffing.